NSDI is a calendar problem disguised as a conference. One edition, two submission
gates, two decision cohorts, and a revision mechanism that spans deadlines — a team
that plans "for NSDI" without naming the gate usually discovers it planned for
neither. Dates below are the NSDI '27 cycle as rendered on 2026-07-08; treat them as
this cycle's snapshot and re-pull the HotCRP /deadlines pages before acting.
| Gate | Date (11:59 pm US EDT) | Cohort |
|---|---|---|
| Spring abstracts | April 16, 2026 | spring |
| Spring full papers | April 23, 2026 | spring |
| Spring notification | July 23, 2026 | spring |
| Fall abstracts | September 10, 2026 | fall |
| Fall full papers | September 17, 2026 | fall |
| Fall notification | December 8, 2026 | fall |
| Symposium | May 11-13, 2027, Providence, RI | both |
Where "today" (2026-07-08) sits: spring authors are two weeks from notification; a fresh submission has nine weeks to the fall abstract gate. Camera-ready dates and the '27 artifact schedule were not yet rendered — 待核实, watch the conference page.
Path A fall '26 submit -> accept (Dec 8) -> final paper + AE -> present May '27
Path B fall '26 submit -> one-shot revision -> resubmit spring '27 (next edition)
Path C fall '26 submit -> reject -> BARRED from spring '27; rework for fall '27
Path D spring '26 one-shot revision (notif Jul 23) -> revise -> fall '26 resubmit
Path C is the one teams forget: a plain rejection carries a one-deadline ban, so the cheapest-looking option — "just submit and see" — silently spends two deadlines, not one. Build the decision into the plan: submit only when the evidence would survive review, otherwise hold for the next gate and use the time on the testbed.
A fall-2026 target, walked backward:
nsdi-experiments). Trace collection and testbed reservations start now — cluster
time is the resource that cannot be compressed in deadline week.nsdi-reproducibility); the paper skeleton fills section by section
(nsdi-writing-style); related-work sweep across both NSDI cohort lists of the
current edition (nsdi-related-work).nsdi-supplementary).nsdi-submission),
uploaded and marked complete with hours to spare.NSDI's review silences are long (spring: April to late July; fall: September to early December). Productive uses that pay off regardless of outcome:
nsdi-artifact-evaluation), and the Community Award requires public code/data by
the final-papers deadline.A one-shot revision arrives with a reviewer-authored list of required issues and a deadline implied by the next submission gate. Run it as a mini-project:
nsdi-author-response).Early in a cycle, spring-vs-fall is a real decision, not a default:
[Target gate] spring / fall + year (papers due <date>)
[Today's position] weeks to next gate; cohort status of any pending submission
[Backward plan] milestone -> week -> owner
[Ban check] any cohort-ban or revision window constraining this plan?
[Wait-time tasks] artifact / testbed / next-paper assignments
[Top schedule risk] <one item + mitigation>