rss-workflow
This guide provides a comprehensive project management framework for submitting research to major robotics conferences, particularly RSS. It maps out the complex annual cycle, from abstract submission to final presentation, detailing critical deadlines, required milestones (like hardware trials and writing drafts), and fallback options at sibling venues (IROS, CoRL, ICRA). Essential for researchers managing time-sensitive academic pipelines.
Get Skill
500 downloads
Overview

RSS Workflow

Project-manage an RSS submission against its real calendar. Anchor every date to the
current edition's pages; the 2026 dates below are a verified historical snapshot
(source map rows 1-3, checked 2026-07-08), not a promise about 2027.

Where the cycle stands right now (as of 2026-07-08)

  • RSS 2026 (22nd edition, Sydney: UTS + ICC) runs July 13-17, 2026 — conference

week starts in days. The submission funnel (abstract Jan 23 → paper Jan 30 →
supplement Feb 6 → invited rebuttal Apr 3 → decisions Apr 27, all AoE) is closed.

  • Accepted authors are in final-presentation mode: talk, poster, travel, and artifact

release (rss-camera-ready, rss-artifact-evaluation).

  • Everyone else is planning RSS 2027, whose site, dates, and deadlines were

unposted at check time (待核实). The recent pattern — late-January deadline, July
conference — is a planning hypothesis only.

The robotics year, seen from RSS

RSS shares its authors with three siblings, so choosing RSS is also choosing a slot in
an annual rotation. Approximate recent geometry (verify each venue's live pages):

VenueTypical deadlineTypical eventWhat slipping past RSS costs
RSSlate JanuaryJulyNext comparable single-track slot is a full year away
IROS~March~OctoberNatural catch for a paper 6 weeks short of RSS-ready
CoRL~June~NovemberRight jury if the learning story dominates
ICRA~September~May/JuneBroadest program; absorbs systems breadth

The practical use: a project that misses the January bar honestly should aim at IROS
or CoRL rather than submit thin — RSS's selectivity makes weak submissions expensive
in reviewer goodwill.

Backward plan to a late-January deadline

Weeks outMilestone for a claim-plus-hardware paper
12+Scientific claim fixed in one sentence; evidence plan sized to it
10Hardware trial campaign running; failure attribution logged from day one
6Ablations that isolate the mechanism complete
4Full draft; supplement storyboard; internal red-team read
2Anonymity sweep of PDF and media; OpenReview metadata entered
1Abstract registered; buffer for robot downtime already spent
0Paper in; supplement due one week later — do not design it that week, only pack it

The one-week paper→supplement gap (2026: Jan 30 → Feb 6) is packing time, not filming
time; footage shot after the deadline cannot support claims already frozen in the PDF.

Conference-week execution (the stage that is live right now)

For teams presenting at the current edition, the final week has its own checklist:

  • Confirm the talk slot, format, and timing against the official program page; a

single-track schedule has no parallel-session slack for overruns.

  • Load footage locally; conference-venue networks are not a playback plan.
  • Push the public artifact release live before the talk — the single-track

audience is the largest referral event the repository will ever get
(rss-artifact-evaluation).

  • Prepare the poster to carry the evidence detail (trial counts, failure

distribution) that the talk compresses away.

  • Assign one author to note every hallway objection; those are free previews of the

journal-extension reviews.

RSS 2027 monitoring plan

Nothing about 2027 was posted at check time. Watch these, in this order, starting
early autumn 2026:

  1. https://roboticsconference.org/ — the banner rebinds to the new edition.
  2. The RSS Foundation calendar page (roboticsfoundation.org).
  3. The OpenReview venue namespace for a RSS/2027 group appearing.
  4. The CFP page for the new deadline cascade and any format change — the 8-page

ceiling and the two-stage rebuttal are both cycle policies, not fixtures.

Stage-specific traps

  • February-March silence: first reviews are not public-scheduled; do not plan

team availability assuming a known release date (待核实 each cycle).

  • The rebuttal is conditional: only papers above a first-round threshold are

invited to respond. Plan an April window in calendars without assuming it will be
used (rss-author-response).

  • April 27 → July is short: visa lead times for the host country can exceed the

decision-to-conference gap; start paperwork at submission time for likely-accept
projects.

  • No standing editors: the Program Chair and Area Chairs rotate per edition (2026

PC chair: Matei Ciocarlie, Columbia — verified 2026-07-08); never carry a name or a
policy across cycles.

Ownership map for a multi-person campaign

Robotics submissions fail at handoffs; name owners early:

WorkstreamSingle owner for
Claim custodyThe one-sentence claim; vetoes scope drift in any section
Trial campaignProtocol document, ledger integrity, daily campaign log
MediaFootage banking from every session; the supplement cut
AnonymityThe sweep across PDF, video, archive, and OpenReview fields
Deadline mechanicsAoE conversions, form fields, upload confirmations

Footage banking deserves emphasis: clips must be captured during the campaign,
because the supplement freezes one week after the paper and reshoots after the
paper deadline cannot support frozen claims.

Output format

[Cycle position] planning 2027 / drafting / submitted / rebuttal window / accepted / conference week
[Next hard date] <date + source URL, or 待核实>
[Critical path] <three tasks gating the next stage>
[Fallback venue] IROS / CoRL / ICRA + trigger condition
[Calendar risks] <robot downtime / visa / footage / rebuttal availability>