Use this as the project-management skill for an IROS submission. Replace every date with the current official timetable and work backward from PaperPlaza cutoffs.
IROS is a conference, not a journal: it has no standing editor-in-chief and no article-processing charge. It is co-sponsored by IEEE RAS and the Robotics Society of Japan (RSJ) — hence "IEEE/RSJ" — and the organizing committee rotates yearly between regions, so re-check the current CFP and committee page rather than carrying names or rules forward. The cost model is registration plus any per-page charge, and proceedings go to IEEE Xplore.
IROS is the fall IEEE-RAS mega-venue, the seasonal counterpart to ICRA's spring cycle. The 2026 edition ran a spring submission into an autumn conference:
Knowing you are on the fall calendar changes routing: a project that misses IROS's spring deadline has CoRL and the next ICRA as nearer alternatives than waiting a full IROS year.
| Weeks out (heuristic) | Real-robot systems milestone |
|---|---|
| 10+ | Platform frozen; task distribution and success criterion defined |
| 8 | Baselines implemented on the same hardware for a fair comparison |
| 6 | Main trials run, resets logged, failures categorized |
| 4 | Sim-to-real study complete; the gap is a number, not a hope |
| 3 | Full draft in IEEE two-column format; references budgeted as content |
| 2 | Video footage banked from real sessions; rough 60 s cut assembled |
| 1 | Anonymity sweep across PDF, figures, and video; PaperPlaza PINs collected |
| 0 | Paper uploaded; video by its separate cutoff |
These offsets are planning heuristics only — anchor each to the current official timetable, never to a previous cycle's calendar.
[Current stage] idea / experiments / writing / submission / video / review / notified / camera-ready
[Next official deadline] <date and source, or unknown>
[Critical path] <three tasks that determine readiness>
[Risk register] <page-budget/anonymity/robot-evidence/video/transfer>
[Owner map] <task -> person or role>